in

NLNG vs MACOBARB: Embattled Contractor In Fierce Cross Examination Made To Read Out Clauses That Warranted N5bn Claim

The fierce cross-examination ongoing in the earthshaking N5bn claims case by Macobarb international against the NLNG moved to a treacherous turn when lead counsel to the defendants (NLNG), Prof Bayo Aderelegbe, demanded that the second defendant, Shedrack Ogboru, should read out to the open court anywhere that the contract signed by both parties warranted the claims of N5bn he is pursuing in court.

This afforded the claimant to read thus: “Exhibit YJ ’12’ (contract agreement) in Section 1 subsection 3.0 in pages 3-4 states: ‘In consideration of the due performance of the works by the contractor and the performance of its other obligations under the contract, the Company shall pay to the contractor all sums in accordance with Section 8 (Schedule of Rates and Prices), as well as other sums or amounts as may become payable to the Contractor pursuant to the provisions of the contract, (herein called the Contract Sum)’.

“By this provision, having given the Defendant notification on the 30th of July 2014 of having placed the contractor, equipment, and personnel idle by repeated payment denials the forensic accountant deposition on oath computed the amount Company owes Contractor up 12th February, 2024, to be over N5bn being the current contract price and still running.”

He said this provided punitive claims against any party that caused delay of work.

Prof Aderelegbe again asked Ogboru to show anywhere approval was given to work done but not paid. To this, Ogboru, CEO of Macobarb, pointed at Exhibit YJ ‘6’, titled ‘Notes of Progress Review Meeting No. 8’ dated 25th June, 2014, showing the various percentages of work done in engineering design, procurement, and construction in the overall summary of work progress as of March 10, 2014 signed by the Contract Holder, Dweller Francis, and which Interim Certificate of payment was not signed. He said this was as an example of first and second milestone certificates approved by the Contract Holder as evidence of work and to be paid by NLNG, saying action was by the intervention of Bayo Adenrele, Head of Project Support Service, who he said was not in any way authorized to truncate the execution of the project. He said Adenrele willfully did so, without the NLNG intervention to stop him.

The fireworks began when counsel for MACOBARB, Nwieke Dignity, pleaded to tender documents relevant to the case before cross-examination. Aderelegbe, counsel for NLNG, however argued that the documents should have been tendered earlier.

See also  Kenyan Legal System Discovers That Lawyer Who Had Won 26 Of All His Cases In Court Is A ”Fake

This Justice, Chiwendu Nwogu of Rivers State High Court, ruled that the day was for continuation of cross examination and that this should continue. The claimants’ counsel however later told the court that he wished to recall his witness (Ogboru) to the witness box for the purpose of laying foundation for admitting some documents that were not yet admitted.

The case, which centres on allegations of contractual breaches, remains highly contentious.

At the heart of MACOBARB’s claim is the assertion that NLNG’s failure to adhere to payment terms caused financial difficulties and equipment downtime.

During further cross-examination, the witness, (Ogboru), when asked if he experienced cash flow issues, maintained that Macobarb experienced cash flow issues, but that these were induced by NLNG’s refusal to make payments as stipulated in the contract agreement.

Despite facing financial strain, the witness denied seeking external financial assistance, although correspondence under the Nigerian Vendor Finance Scheme (NDFS) was presented as a request for support from NLNG.

A significant point in the proceedings is the presentation of Exhibit YJ6, which detailed that MACOBARB had completed 74.8% of the contracted work by March 10, 2014. The witness also referenced other exhibits, including YJ40 and YJ21, to substantiate claims of completed milestones and partial payments.

See also  Voters, Residents Of Abuja File Suit Challenging Tinubu Swearing In

According to the witness, the agreed N95 million payment for completed work was delayed, and NLNG made only partial milestone payments, leaving Macobar with substantial losses.

The court also heard testimony regarding the role of NLNG’s contract holder, described as the sole representative authorized to approve work, provide instructions, and confirm satisfactory completion.

The witness confirmed that NLNG’s payments were contingent upon both the completion of assigned tasks and the contract holder’s approval, as outlined in the contractual terms.

Another key focus was the N5 billion claim, which the witness explained that it represents outstanding payments and compensation for equipment idle-time caused by NLNG’s alleged breaches.

It was revealed that equipment remained idle from July 30, 2014, until February 12, 2024, despite Macobarb notifying NLNG of the situation.

The case has drawn significant attention due to its implications for corporate accountability and adherence to contractual obligations in Nigeria’s energy sector. With cross-examination ending Friday January 17, 2025, the court’s decision would hinge on the weight of the evidence provided, including whether MACOBARB satisfactorily completed the work and whether NLNG’s actions justified the substantial claim.
By Anita Ogona

Leave a Reply

Your email address will not be published. Required fields are marked *

GIPHY App Key not set. Please check settings

Supreme Court Fixes Feb.10th To Hear Five Separate Cases Instituted By Rivers Gov Against Wike’s Camp

What President Trump Said About Bishop’s Call for Mercy on LGBTQ+ Migrant Workers